D-8 Sample Migration Task Lists
Parallel Migration Task List Example Adaptive Server Enterprise 11.5
5. Retest as necessary.
6. Document capacity test results.
7. Obtain user signoff on capacity test results.
Perform User Acceptance Tests
1. Perform acceptance tests.
2. Compare acceptance test results to baseline.
3. Analyze acceptance test results.
4. Perform corrective actions.
5. Retest as necessary.
6. Document acceptance test results.
7. Obtain user signoff on acceptance test results.
Perform Production Data Refresh
1. Schedule production data cutover.
2. Extract production data.
3. Move data to target.
4. Load data into Adaptive Server production environment.
5. Backup new environment.
6. Notify users of data refresh.
Parallel Migration Task List Example
This sample task list covers a parallel migration with replication
approach to upgrade SQL Server 10.x to Adaptive Server11.5.
The scenario for this task list is:
A major telecommunications company cannot afford system
downtime for the upgrade.
In the event of failure, the system cannot be down more than 15
minutes and cannot afford more than 1 hour of data loss. The
migration must support these contingency requirements if a
production back-out is required.
This example does not repeat the preparation steps to given in the
previous example.